J & T Allan – Dining and Lounge Renovation

By Jade Spinford

What a journey this project has been.

This project started in mid December 2017, when I was 8 months pregnant and has only just finished now. My beautiful baby girl is now 2 months old.

Here is a run down of the idea process, time frames and costings as well as lots of photos.

In the first meeting with J&T Allan we discussed what was important to them, what they wanted to keep and what they were happy to part with.

Using this information I came up with three designs to show them at the next meeting.

A detailed pack was given for each design. From these three we decided on a final look.

Before Photos

Points of change

  • timber flooring in dining
  • new carpet in lounge
  • style change to balustrade
  • new lounges
  • recovering dining chairs
  • paint both rooms and entrance
  • recover pelmets
  • wall lights, lamps and pendant
  • skirting
  • mock wall to house a new gas log fireplace
  • cabinets either side of mock wall
  • recover tub chairs

This project should have, in normal circumstances taken 6-8 weeks. The Allan’s were very gracious to allow the extended time for this project.

I think you will agree that with the changes made have brightened the rooms, as well as given a more contemporary look whilst still incorporating the existing jarrah furniture.

After Photos

Share This:

Share on facebook
Share on twitter
Share on linkedin
Share on pinterest
Share on whatsapp
Share on email

More
articles

Request a Consultation
Contact Jade
Scroll to Top